Gym Building Update (June 28, 2024)
Posted On 28 June 2024
Our building project is on full hustle as the weather is good and our vendors are eager to keep going in a forward direction.
The metal building folks put in all the windows on the gym portion of the building and have finished with weather tight of those windows.
Our site looks extremely busy (see photos and videos).
Our site crew has been on site all week and had 75% of the underground trenching completed for the water, sewer and electrical infrastructure. The piping for sprinkler service is 50% complete.
Work will continue on the site work during the upcoming week.