Gym Building Update (August 2, 2024)

This week saw onsite work of the following:

Bellco, our site contractor, was finishing the current phase of site work they are doing.  

We now have the following items brought to conclusion:

  • Propane underground storage
  • Propane pipe chas to new building
  • Generator concrete pad poured
  • Check dams on high tide of building installed
  • Storm drainage pond establishes
  • All underground electrical backfill
  • All underground sprinkler water line backfill
  • All underground domestic water backfill
  • Septic line to septic tank
  • Septic tank installed
  • Full backfill of the right side of buildng and grass seed planted
  • Parking lot, right side, rough grade

Osgood construction continues to finish the trim on the building.

Off site we have the price for the doors and windows being prepared
Off site we have the pricing on the concrete pad for the entry way being prepared