Gym Building Update (September 6, 2024)

The construction site continues to be a buzz.

The siding is 100% complete.  The roof and trim is 100% complete.

At this time the post and beam entry frame is being fabricated to be delivered in three weeks.

Next week sees the concrete pad for the post and beam entry to be poured.

At this time we are getting final prices and ordering the front windows, celestry windows, front door and side and rear doors.

These items have about a 6 week lead time.

We look to begin back fill of the interior of the building in two weeks.