Gym Building Update (October 4, 2024)
Posted On 4 October 2024
This week saw the new Post and Beam entrance getting its trim boards on.
Concurrent with that the pine boards for the ceiling of the post and beam have been manufactured and are being cut to size.
Septic system has been ordered and due on site in two weeks.
We are currently evaluating the front door, windows, clearstory windows and gymnasium doors for final purchase.