Gym Building Update (October 18, 2024)

Bellco Excavation was on site.  It completed the septic system for the gymnasium.  They have finished 80% of the outside work on the yards and parking lots.  Interior work was to support the plumbers.

Plumbers are onsite and did all of the under floor septic and venting service that needed to be done.  The work will be inspected on Tuesday and then backfill of the gym floor will occur.  

We expect the backfill of the gym floor to be completed by next weekend.

Budel Construction was on site and measured for the final roof for the post and beam entry.