Gym Building Update (November 1, 2024)
Posted On 1 November 2024
This week was exciting on campus as the new gymnasium building received its permanent electricity. We now are hooked to the electric grid via Eversource and are underway for lifelong operation.
Our electrical contact, Daniels, continued to run the wiring for the overhead lights in the gymnasium. They also continued to run the wiring for the fire alarm system in the walls and ceiling areas.
We have lined up concrete for November 18 for the floor of the gym.
We have windows, doors and gym doors in final preparations for ordering.
The roof for the post and beam entry is ordered and in the que for installation.