Gymnasium & Field House

CONSTRUCTION IS WELL UNDERWAY for the Gymnasium and Field House at our Saint Methodios Faith and Heritage Center–the Home of MBC! Indoor basketball, soccer and much more!!!

CALLING ALL MBC/BDC ALUMNI, FAMILY AND FRIENDS…..

OUR CAMP NEEDS YOUR HELP to finish the Gym Building Project and to make this dream a reality! Thousands of campers, staff and young adults will enjoy this state-of-the-art gymnasium for generations to come!

PLEASE JOIN US BY DONATING NOW!!!
THANK YOU!

Building Plans

  • Gym Exterior
  • Gym interior
  • Lobby 1
  • St Methodios Gym_Level 1 Plan_9-26-2023
  • Lobby page 3?

Latest Update

  • Gym Building Update (November 15, 2024)

    Work is progressing smoothly on the gymnasium project as we begin to do the final button up of the exterior of the building in anticipation of final finishes over the winter inside the building.

    This week saw the arrival of the under floor insulation for our large floor.

    We have confirmed the concrete floor will go down the week of November 25.  Final pour the first week of December.

    Windows are ordered and expected the second week of December.

    Metal doors for the gym are ordered and expected the second week of December.

    We are finalizing the front door effort and it should be onsite the 20th of December.

    Site work is 90% complete leaving the paving to be finished first thing in the spring!!!!