Gymnasium & Field House
CONSTRUCTION IS WELL UNDERWAY for the Gymnasium and Field House at our Saint Methodios Faith and Heritage Center–the Home of MBC! Indoor basketball, soccer and much more!!!
CALLING ALL MBC/BDC ALUMNI, FAMILY AND FRIENDS…..
OUR CAMP NEEDS YOUR HELP to finish the Gym Building Project and to make this dream a reality! Thousands of campers, staff and young adults will enjoy this state-of-the-art gymnasium for generations to come!
PLEASE JOIN US BY DONATING NOW!!!
THANK YOU!
Building Plans
Latest Update
- Gym Building Update (November 15, 2024)
Work is progressing smoothly on the gymnasium project as we begin to do the final button up of the exterior of the building in anticipation of final finishes over the winter inside the building.
This week saw the arrival of the under floor insulation for our large floor.
We have confirmed the concrete floor will go down the week of November 25. Final pour the first week of December.
Windows are ordered and expected the second week of December.
Metal doors for the gym are ordered and expected the second week of December.
We are finalizing the front door effort and it should be onsite the 20th of December.
Site work is 90% complete leaving the paving to be finished first thing in the spring!!!!
Previous Updates
- Gym Building Update (November 15, 2024)Work is progressing smoothly on the gymnasium project as we begin to do the final button up of the exterior of the building in anticipation… Read more: Gym Building Update (November 15, 2024)
- Gym Building Update (November 8, 2024)This week saw BELLCO Excavation finishing all the prep work for the interior of the building. We are now ready for floor concrete pour. Exterior… Read more: Gym Building Update (November 8, 2024)
- Gym Building Update (November 1, 2024)This week was exciting on campus as the new gymnasium building received its permanent electricity. We now are hooked to the electric grid via Eversource… Read more: Gym Building Update (November 1, 2024)
- Gym Building Update (October 25, 2024)This week at St. Methodios gym project we had a full contingent of site work going on. The parking lot behind the cafeteria, where our… Read more: Gym Building Update (October 25, 2024)
- Gym Building Update (October 18, 2024)Bellco Excavation was on site. It completed the septic system for the gymnasium. They have finished 80% of the outside work on the yards and… Read more: Gym Building Update (October 18, 2024)
- Gym Building Update (October 11, 2024)This past week we saw the temporary power wiring brought in for the interior construction effort. (We await Eversource to energize the line). This coming… Read more: Gym Building Update (October 11, 2024)
- Gym Building Update (October 4, 2024)This week saw the new Post and Beam entrance getting its trim boards on. Concurrent with that the pine boards for the ceiling of the… Read more: Gym Building Update (October 4, 2024)
- Gym Building Update (September 27, 2024)The final connections for electrical from the main Eversource electrical pole has been completed. Eversource will be energizing the pole next week. All final electrical… Read more: Gym Building Update (September 27, 2024)
- Gym Building Update (September 20, 2024)This week saw the complete backfill of the inside of the building. We are now at sub grade. In the next month we will be… Read more: Gym Building Update (September 20, 2024)
- Gym Building Update (September 13, 2024)Good day——This week has been a very productive week at the St. Methodios gym project. The Post and Beam structure is under construction offsite and… Read more: Gym Building Update (September 13, 2024)
- Gym Building Update (September 6, 2024)The construction site continues to be a buzz. The siding is 100% complete. The roof and trim is 100% complete. At this time the post… Read more: Gym Building Update (September 6, 2024)
- Gym Building Update (August 23, 2024)The site continues to have progress made in the following areas. The main electoral connection from the pole to the site disconnect has been installed… Read more: Gym Building Update (August 23, 2024)
- Gym Building Update (August 9, 2024)This week saw the completion of the exterior trim. We are now 50% done with the interior trim. The post and beam entrance is in… Read more: Gym Building Update (August 9, 2024)
- Gym Building Update (August 2, 2024)This week saw onsite work of the following: Bellco, our site contractor, was finishing the current phase of site work they are doing. We… Read more: Gym Building Update (August 2, 2024)
- Gym Building Update (July 26, 2024)Good day. Herewith the report for the Juiy 26, 2024 progress on the gymnasium for St. Methodios. This week saw the following: We look forward… Read more: Gym Building Update (July 26, 2024)
- Gym Building Update (July 19, 2024)Good day fellow friends of St. Methodios. This week we saw the last of the trim going on the building. The wonderful looking white trim… Read more: Gym Building Update (July 19, 2024)
- Gym Building Update (July 12, 2024)Good day—We are pleased once again to report excellent progress this week on our gymnasium project. During this week we pulled the electric, data, domestic… Read more: Gym Building Update (July 12, 2024)
- Gym Building Update (July 5, 2024)Good day. This weeks report can be best told in the old saying, “A picture is worth a thousand words”. We have had great… Read more: Gym Building Update (July 5, 2024)
- Gym Building Update (June 28, 2024)Our building project is on full hustle as the weather is good and our vendors are eager to keep going in a forward direction. The… Read more: Gym Building Update (June 28, 2024)
- Gym Building Update (June 21, 2024)The equipment for site work has returned to the site and work commences in earnest on Monday. The first order of business is to bring… Read more: Gym Building Update (June 21, 2024)
- Gym Building Update (June 14, 2024)This week saw the construction site being cleaned up of all minor debris in anticipation of the site contractor returning in full swing next week.… Read more: Gym Building Update (June 14, 2024)
- Gym Building Update (June 7, 2024)Good day to all. This is the weekly report for June 7, 2025 for the St. Methodios gym project. We continue to be blessed with… Read more: Gym Building Update (June 7, 2024)
- Gym Building Update (May 31, 2024)Good day. Herewith the May 31 update for our construction project at the Contoocook center. The steel building frame, roof and siding is 95% complete.… Read more: Gym Building Update (May 31, 2024)
- Gym Building Update (May 24, 2024)A sweltering week accompanied the Osgood Construction steel workers who finished the siding of the Welcome Center – Lobby. Budel crews installed the remaining stone… Read more: Gym Building Update (May 24, 2024)